Hi Experts - We are creating an STO in Brazil where stock is moving from 1 plant to another plant.
Current ATP situation is as follows: which shows 22 EA still available.
We are creating the STO from the plant 3004 to plant 3005.
We are confused why the system is proposing the delivery date of March 17 instead of March 14, in spite of sufficient quantity being available.
We do understand that it takes 03/17/2014 because of the upcoming weekend. But when stock is available on March 14, we would have expected this result.
These are the key configurations that I have done:
Material Master:
MRP View: Planned Delivery Time is 0
MRP Type: PD (MRP)
Checking Group: 02
Assign delivery type and checking rule config for Material Master is also done as follows:
Request your help please!
Regards