Problem with "Material Planning in Networks"

$
0
0

I want to use the Mat. Planning field of an activity to do preliminary material cost planning as I do not know the exact cost of my components right away. Several months from now once Engineering has released a spec and we get a quote from a vendor we will add the component to the network and give it a real price.

 

According to F1 help of this Mat. Planning field, it sounds like exactly what I need:

  • Tcode: CJ20N
  • Choose activity -> assignments tab -> Mat Planning field
    Screen Shot 2014-03-25 at 4.05.27 PM.png
  • The help says:
    Screen Shot 2014-03-25 at 4.07.29 PM.png

Perfect, that sounds exactly what I want.

To test, I did the following:

  • Enter $1,000 in my Mat Planning
  • Add a component to the activity:
    Screen Shot 2014-03-25 at 4.09.10 PM.png
  • Run MRP to create requisition
  • Set price of $900 in requisition

 

 

I then ran PS Report S_ALR_87013533 to check the planned costs, and this is what it gave:

Screen Shot 2014-03-25 at 4.12.08 PM.png

  • Plan: $1070 - O.K.(the 1000 I planned plus $70 which is an automatic 7% material overhead that the system calculates)
  • Actual: $0 - O.K. (No GR or IR yet)
  • Commitment: $900 - O.K.(I have a requisition for this amount)
  • RemOrdPlan $1070 - Not O.K.? (I would have expected this to be 1070 - 900 = $170, but I'm not certain what RemOrderPlan represents)
  • Assigned: $1970 - Not O.K. (i've only assigned 900?)
  • Available: -$900 - Not O.K. (I have $170 available)

 

It looks like I have an overrun of $900, which is incorrect.

What did I do wrong? Why doesn't the expected material cost of $170 appear in this report? (Am I using the wrong report?)