Hi PS Guru,

 

Good Day!

 

Issue: The purchase order is about 80% completed already but we noticed in PS budget reporting, the delivered/invoiced amount doesn't reflect under the actual column of CN41N.

 

Cause: Per checking, the actual incurred was manually settled using an FI tcode ( FB01) instead of settlement through CJ88.

 

Question: How can we reflect the actual amount in CN41N given that it is manually settled through FB01. Thank you

 