Hi Gurus,
I need separate MRP PR for each requirements of Safety stock and Customer order but both requirements combined and generated single MRP PR. Kindly provide the solution for the same.
Example :
Stock is available for material 102.70
Safety stock - 200
Customer order - 2.20
One PR is required against safety stock = Safety stock - Stock = 200 -102.70 = 99.30
Another PR is required against Customer order = 2.20
But System is created a single PR of 99.5 for against both requirements.
Herewith attached MD04 screen shot and material master configuration screen shot for your reference.
MD04
MM03
Regards