MD04: Forecasts display as unplanned requirement.

Hi expert;

 

I am preparing implementing planning on consumption and reorder point (MRP Type VB). For this I created the forecast view for purchased material and I performed the generation of forecasts.

 

I found that the values of the forecast are displayed in MD04 as unplanned requirement for all periods.  I do not want these forecasts appear as unplanned requirement because buyers risk into account to supply the stock.

 

Is there a setting that forecasts are taken into account as unplanned requirement and apparaisses not in the MD04?

 

For now, I put zero to all forecast, of this made won't appear in the MD04

 

Thanks in advance and Kind regard