Hi Gurus,
If I select the following MRP run parameters in MD02 then it creates Planned orders instead of purchase requisition for future demands. Parameters are following:
1. Processing key: NETCH
2. Create Pur req: 2
3. Delivery Schedule: 3
4. Create MRP list: 1
5. Planning Mode: 1
6. Scheduling: 1
So, it creates Planned order outside the opening period. But, we want that by keeping this setting intact in MD02 is there any way that a particular material will create Pur Req all the time. I have already tried: by creating MRP group and assigning that to a material and maintained creation indicator as create pur req = 1 in OPPR. But this setting is overridden by the MD02 setting and it creates planned order out of the opening period. So, my question: Is there any way to override the MRP setting in MD02 and always create Pur Req. after MRP run.
Thanks for your response,
Tanveer